Every complaint on the public K-RERA list, linked back to the registered project where the certificate number or name matches. A final order means the Authority or Adjudicating Officer has decided; the order text itself is on the portal.
Complaints listed
2,414
as of 12 Oct 2026
Final orders
1,232
51% decided
On registered projects
1,178
207 projects
Not matched to register
1,236
no project id join — not a finding that the project is illegal
Complaints by year
Feed
2,414 matching · page 2 of 49. “Not matched” means we could not join the complaint row to a register project id — not a finding that the project is illegal or unregistered.
95/2026pending
M/s Suraksha and 2 Others
Authority09 Aug 2026
94/2026pending
Life Line Green Citynot matched to register
M/s Realine Properties Pvt Ltd and 13 Others
Authority09 Aug 2026
93/2026pending
Life Line Green Citynot matched to register
M/s Realine Properties Pvt Ltd and 13 Others
Authority09 Aug 2026
92/2026pending
Life Line Green Citynot matched to register
M/s Realine Properties Pvt Ltd and 13 Others
Authority09 Aug 2026
89/2026pending
Historic Wynanot matched to register
M/s Historic Homes Private Limited and 2 Others
Authority05 Aug 2026
87/2026pending
Venice Lamcynot matched to register
M/s Dena Homes and Developers Pvt Ltd and 2 Others
Authority31 Jul 2026
85/2026pending
Sahara Grace Kochinot matched to register
M/s Sahara Prime City Limited and 7 Others
Authority30 Jul 2026
84/2026pending
Sahara Grace Kochinot matched to register
M/s Sahara Prime City Limited and 7 Others
Authority30 Jul 2026
final order
—not matched to register
Authority28 Jul 2026
final order
—not matched to register
Authority28 Jul 2026
81/2026pending
M/s Sobha Parvathi Ajith Consultant Engineers & Builders Pvt Ltd and 3 Others
Authority24 Jul 2026
pending
TestPnot matched to register
testR
Authority24 Jul 2026
79/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
78/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
77/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
76/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
75/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
74/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
73/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
72/2026pending
M/s Travancore Builders Private Limited
Authority15 Jul 2026
71/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
70/2026pending
M/s Travancore Builders Private Limited & 9 Others
Authority15 Jul 2026
2/2026pending
M/s Anta Builders and Developers Pvt Ltd and 7 others
Adjudicating Officer15 Jul 2026
1/2026pending
M/s Anta Builders and Developers Pvt Ltd and 7 others
Adjudicating Officer14 Jul 2026
69/2026pending
Sahara Grace Kochinot matched to register
M/s Sahara Prime City Limited and 7 Others
Authority10 Jul 2026
68/2026pending
M/s Salim Associate Builders & Developers (P) Ltd and 3 Others
Authority02 Jul 2026
66/2026pending
M/s Anta Builders and Developers Pvt Ltd and 5 Others
Authority01 Jul 2026
8/2026final order
—not matched to register
M/s Sowparnika Projects and Infrastrucure Pvt Ltd and another
Adjudicating Officer01 Jul 2026
4/2026final order
—not matched to register
Tata Realty and Infrastructure Ltd and another
Adjudicating Officer01 Jul 2026
63/2026pending
Mount Aranyamnot matched to register
M/s Sree Mount Builders and Developers Pvt Ltd and Other
Authority29 Jun 2026
62/2026pending
M/s Sree Mount Builders and Developers Pvt Ltd and Other
Authority29 Jun 2026