On Track2 complaints · 1 order

Sobha Limited · Apartments · ERNAKULAM, Ernakulam · K-RERA/PRJ/ERN/076/2023

Physical progress
62%
listing 62% · folder 61%
Proposed completion
30 Oct 2028
no date change on file
Units booked
98%
190 of 193
Quarterly update
Current
Q2 2026 · filed 07 Oct 2026 · -34d ago

As filed with K-RERA

Registration
K-RERA/PRJ/ERN/076/2023
granted 28 Apr 2023
Promoter
Sobha Limited
Location
ERNAKULAM, Ernakulam, 682018
Type
Apartments
2 building(s)
Plot area
67,558 sqm
Registered floor area
76,633 sqm
≈ 8,24,867 sqft · residential 76,633 sqm · other 0 sqm
Units
193
193 residential
Project start
15 Mar 2016
Proposed completion
30 Oct 2028
Extension
—
Physical progress
62%
As on 30th Sep'2026
Financial progress
94%
As on 30th Sep'2026
Escrow bank
ICICI Bank
Financier
—
Complaint
No
Legal case
No
Authority order
No

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 06 Jul 2026
filed
Engineer Form 3
latest 07 Jul 2026
filed
CA Form 4
latest 07 Jul 2026
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

2 of 2 open on K-RERA
Collected FY 2024–25
₹142.0 Cr
₹1,41,98,72,571 as filed
Deposited
₹99.4 Cr
70.0% of collected
Withdrawn
₹100.2 Cr
from the separate account
Closing (year-end)
₹10.7 L
FY 2024–25 closing — not today’s balance
Separate account

FY 2024–25 Form 5 · as filed 30 Oct 2025 · read via OCR · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹94,76,548
Collected from allottees
₹1,41,98,72,571
Deposited in separate account
70.0% of collected
₹99,39,10,800
Withdrawn
₹1,00,23,17,008
Closing
₹10,70,340
withdrawn ₹1,00,23,17,008year-end leftover ₹10,70,340

Closing is 0.1% of money that went through the separate account (opening + deposited). 70.0% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

FY 2024–25
filed 30 Oct 2025 · file 181419
₹1,41,98,72,571 in
Filed 28 Oct 2024
file 137239
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

1 of 2 decided
6/2026final order
Sobha Limited and 2 others
Adjudicating Officer31 Jul 2026
107/2025pending
M/s Sobha Ltd and 2 Others
Authority28 Jul 2025

RAID

2 from register
TypeSignalSeveritySourceStatus
I
2 complaints filed with K-RERA, 1 final order
↳ Latest 6/2026 · Adjudicating Officer · 2026-07-31
HighK-RERAOpen
A
Spend running ahead of build
↳ Financial 94% vs physical 62%
MediumK-RERAOpen