Homestead Projects And Developers Private Limited

Portfolio of 2 registered projects · Malappuram · register read 12 Oct 2026

Projects
2
1 completed
Active
1
Overdue
1
past promised date
Complaints · cases
0 · 0
QPR current
0%
active projects filed in 120d
Units booked
113%
162 of 144 · 22,183 sqm

Status mix

Quarterly filing discipline

Projects

sorted by promised completion

RAID

2 from register
TypeProjectSignalSeveritySourceStatus
RHOMESTEAD RIVERINE
Homestead Projects And Developers Private Limited
6 months past proposed completion
↳ Proposed 2026-02-28, physical progress 55%
MediumK-RERAOpen
DHOMESTEAD RIVERINE
Homestead Projects And Developers Private Limited
Quarterly update is stale
↳ Last filed 2026-01-07 (Q3 2025)
LowK-RERAOpen