Homestead Projects And Developers Private Limited · Apartments · PANAKKAD, Malappuram · K-RERA/PRJ/218/2020

Physical progress
55%
filed 14 Oct 2023
Proposed completion
28 Feb 2026
6 months past
Units booked
58%
84 of 144
Quarterly update
Stale
Q3 2025 · filed 07 Jan 2026 · 239d ago

As filed with K-RERA

Registration
K-RERA/PRJ/218/2020
granted 28 Jul 2021
Promoter
Homestead Projects And Developers Private Limited
Location
PANAKKAD, Malappuram, 676519
Type
Apartments
2 building(s)
Plot area
3,783 sqm
Registered floor area
14,461 sqm
≈ 1,55,654 sqft · residential 14,461 sqm · other 0 sqm
Units
144
144 residential
Project start
—
Proposed completion
28 Feb 2026
Extension
—
Physical progress
55%
Financial progress
49%
Escrow bank
Dhanlaxmi Bank
Financier
Dhanlaxmi Bank
Complaint
No
Legal case
No
Authority order
No

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 13 Jan 2026
filed
Engineer Form 3
latest 13 Jan 2026
filed
CA Form 4
latest 06 Aug 2025
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

5 of 5 open on K-RERA
Collected FY 2023–24
₹2.9 Cr
₹2,89,05,173 as filed
Deposited
₹21.8 L
7.5% of collected
Withdrawn
₹3.1 Cr
from the separate account
Closing (year-end)
₹2.7 L
FY 2023–24 closing — not today’s balance
Separate account

FY 2023–24 Form 5 · as filed 29 Oct 2024 · read via OCR · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹2,89,05,173
Collected from allottees
₹2,89,05,173
Deposited in separate account
7.5% of collected
₹21,78,159
Withdrawn
₹3,08,17,331
Closing
₹2,66,001
withdrawn ₹3,08,17,331year-end leftover ₹2,66,001

Closing is 0.9% of money that went through the separate account (opening + deposited). 7.5% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

Filed 31 Oct 2025
file 181678
PDF on K-RERA · not parsed
FY 2023–24
filed 29 Oct 2024 · file 137509
₹2,89,05,173 in
Filed 02 Nov 2023
file 101463
PDF on K-RERA · not parsed
FY 2021–22
filed 05 Nov 2022 · file 75964
₹1,50,06,100 in
FY 2020–21
filed 10 Nov 2021 · file 41899
₹20,99,000 in

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

2 from register
TypeSignalSeveritySourceStatus
R
6 months past proposed completion
↳ Proposed 2026-02-28, physical progress 55%
MediumK-RERAOpen
D
Quarterly update is stale
↳ Last filed 2026-01-07 (Q3 2025)
LowK-RERAOpen