PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED

Portfolio of 2 registered projects · Ernakulam · register read 12 Oct 2026

Projects
2
1 completed
Active
1
Overdue
1
past promised date
Complaints · cases
2 · 0
QPR current
0%
active projects filed in 120d
Units booked
53%
29 of 55 · 16,418 sqm

Status mix

Quarterly filing discipline

Projects

sorted by promised completion

RAID

5 from register
TypeProjectSignalSeveritySourceStatus
IECOPARADISE
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
2 complaints filed with K-RERA
↳ Latest 113/2025 · Authority · 2025-07-30
HighK-RERAOpen
RTREESA GARDENS
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
Completion date moved by 24 months
↳ 2023-03-01 → 2025-02-28
HighK-RERAOpen
RTREESA GARDENS
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
18 months past proposed completion
↳ Proposed 2025-02-28, physical progress 94%
HighK-RERAOpen
RECOPARADISE
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
Completion date moved by 6 months
↳ 2021-03-31 → 2021-09-30
MediumK-RERAOpen
DTREESA GARDENS
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
Quarterly update is stale
↳ Last filed 2025-01-07 (Q3 2024)
LowK-RERAOpen