TREESA GARDENS

Overdue

PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED · Villas · EDAPPALLY SOUTH, Ernakulam · K-RERA/PRJ/155/2021

Physical progress
94%
filed 29 Jul 2023
Proposed completion
28 Feb 2025
18 months past
Units booked
100%
12 of 6
Quarterly update
Stale
Q3 2024 · filed 07 Jan 2025 · 604d ago

As filed with K-RERA

Registration
K-RERA/PRJ/155/2021
granted 09 Dec 2021
Promoter
PAUL ALUKKAS DEVELOPERS PRIVATE LIMITED
Location
EDAPPALLY SOUTH, Ernakulam, 682026
Type
Villas
15 building(s)
Plot area
4,047 sqm
Registered floor area
3,199 sqm
≈ 34,438 sqft · residential 3,075 sqm · other 124 sqm
Units
6
6 residential · 30 plots
Project start
—
Proposed completion
28 Feb 2025
previously 01 Mar 2023
Extension
—
Physical progress
94%
Financial progress
95%
Escrow bank
STATE BANK OF INDIA
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 16 Nov 2023
filed
Engineer Form 3
unable to find
not found
CA Form 4
latest 16 Nov 2023
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
on file
filed

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

5 of 5 open on K-RERA
Collected FY 2023–24
₹4.4 Cr
₹4,44,46,943 as filed
Deposited
₹3.1 Cr
70.0% of collected
Withdrawn
₹1.8 Cr
from the separate account
Closing (year-end)
₹1.3 Cr
FY 2023–24 closing — not today’s balance
Separate account

FY 2023–24 Form 5 · as filed 31 Oct 2024 · read via OCR · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹442
Collected from allottees
₹4,44,46,943
Deposited in separate account
70.0% of collected
₹3,11,12,861
Withdrawn
₹1,80,58,000
Closing
₹1,30,55,303
withdrawn ₹1,80,58,000year-end leftover ₹1,30,55,303

Closing is 42.0% of money that went through the separate account (opening + deposited). 70.0% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

FY 2023–24
filed 31 Oct 2024 · file 137900
₹4,44,46,943 in
FY 2022–23
filed 06 Nov 2023 · file 101697
₹5,43,45,018 in
FY 2022–23
filed 06 Nov 2023 · file 101698
₹5,43,45,018 in
FY 2021–22
filed 31 Oct 2022 · file 75445
₹10,24,55,636 in
FY 2020–21
filed 26 Mar 2022 · file 51063
₹1,89,35,669 in

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

3 from register
TypeSignalSeveritySourceStatus
R
Completion date moved by 24 months
↳ 2023-03-01 → 2025-02-28
HighK-RERAOpen
R
18 months past proposed completion
↳ Proposed 2025-02-28, physical progress 94%
HighK-RERAOpen
D
Quarterly update is stale
↳ Last filed 2025-01-07 (Q3 2024)
LowK-RERAOpen