Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
Sobha Bela Encosta Phase-1
CompletedStatus is from the dates they filed. Not a court finding.
Building
Sobha Bela Encosta Phase-1
Who is building it
Sobha Limited
Official number
K-RERA/PRJ/140/2021 · 21 Jul 2021
Where
KUTTIKKATTOOR, Kozhikode, 673008
Type
Villas
Promised ready date
30 Jun 2025
they did not change this date on file
How much they say is done
100%
this is what they filed on 29 Oct 2022
How many already sold
30 of 41
73% flats sold
Complaints
5
3 already decided
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
41
Booked count
30
Escrow bank
Union Bank of India
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 31 Oct 2025.
Collected
₹4,37,53,000
Deposited
₹3,06,27,100 · 70.0% of collected
Withdrawn
₹3,06,08,163
Closing
₹54,376 · year-end, not today
Complaints before K-RERA · 5
175/2023 · Authority
final order
180/2021 · Authority
final order
137/2021 · Adjudicating Officer
final order
132/2021 · Adjudicating Officer
pending
19/2020 · Authority
pending