HiLITE OLYMPUS
CompletedStatus is from the dates they filed. Not a court finding.
Building
HiLITE OLYMPUS
Who is building it
HiLITE Builders Pvt Ltd
Official number
K-RERA/PRJ/KKD/110/2022 · 02 Jul 2022
Where
OLAVANNA, Kozhikode, 673014
Type
Apartments
Promised ready date
31 Dec 2026
they did not change this date on file
How much they say is done
100%
they have not filed how much is done
How many already sold
503 of 526
96% flats sold
Complaints
6
1 already decided
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
526
Booked count
503
Escrow bank
Axis Bank
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 31 Oct 2025.
Collected
₹1,54,74,09,587
Deposited
₹1,09,01,60,307 · 70.5% of collected
Withdrawn
₹98,22,59,900
Closing
₹10,80,11,223 · year-end, not today
Complaints before K-RERA · 6
33/2025 · Authority
pending
178/2024 · Authority
pending
177/2024 · Authority
pending
176/2024 · Authority
pending
21/2024 · Authority
pending
73/2020 · Adjudicating Officer
final order