HiLITE OLYMPUS

Completed6 complaints · 1 order

HiLITE Builders Pvt Ltd · Apartments · OLAVANNA, Kozhikode · K-RERA/PRJ/KKD/110/2022

Physical progress
100%
not filed
Proposed completion
31 Dec 2026
no date change on file
Units booked
96%
503 of 526
Quarterly update
N/A
Q2 2026 · filed 03 Sept 2026 · 0d ago

As filed with K-RERA

Registration
K-RERA/PRJ/KKD/110/2022
granted 02 Jul 2022
Promoter
HiLITE Builders Pvt Ltd
Location
OLAVANNA, Kozhikode, 673014
Type
Apartments
1 building(s)
Plot area
35,003 sqm
Registered floor area
118k sqm
≈ 12,70,027 sqft · residential 118k sqm · other 0 sqm
Units
526
526 residential
Project start
18 Jun 2022
Proposed completion
31 Dec 2026
Extension
—
Physical progress
100%
Financial progress
66%
Escrow bank
Axis Bank
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

5 of 5 filed
Architect Form 2
latest 03 Sept 2026
filed
Engineer Form 3
latest 03 Sept 2026
filed
CA Form 4
latest 03 Sept 2026
filed
Promoter Form 6
latest 05 Sept 2026
filed
Occupancy certificate
on file
filed

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

3 of 3 open on K-RERA
Collected FY 2024–25
₹154.7 Cr
₹1,54,74,09,587 as filed
Deposited
₹109.0 Cr
70.5% of collected
Withdrawn
₹98.2 Cr
from the separate account
Closing (year-end)
₹10.8 Cr
FY 2024–25 closing — not today’s balance
Separate account

FY 2024–25 Form 5 · as filed 31 Oct 2025 · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹1,10,816
Collected from allottees
₹1,54,74,09,587
Deposited in separate account
70.5% of collected
₹1,09,01,60,307
Withdrawn
₹98,22,59,900
Closing
₹10,80,11,223
withdrawn ₹98,22,59,900year-end leftover ₹10,80,11,223

Closing is 9.9% of money that went through the separate account (opening + deposited). 70.5% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

FY 2024–25
filed 31 Oct 2025 · file 181638
₹1,54,74,09,587 in
FY 2023–24
filed 31 Oct 2024 · file 137917
₹1,06,76,62,808 in
FY 2022–23
filed 31 Oct 2023 · file 101131
₹53,61,15,118 in

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

1 of 6 decided
33/2025pending
M/s Hilite Builders Pvt Ltd & 2 Others
Authority27 Feb 2025
178/2024pending
Saidalavi Karuthedath
Authority23 Oct 2024
177/2024pending
Siddeeque Cholakkal
Authority23 Oct 2024
176/2024pending
Shoukathali K.T
Authority23 Oct 2024
21/2024pending
M/s Hilite Builders Pvt Ltd
Authority06 Mar 2024
73/2020final order
P. Sulaiman, Chairman and MD
Adjudicating Officer—

RAID

1 from register
TypeSignalSeveritySourceStatus
I
6 complaints filed with K-RERA, 1 final order
↳ Latest 33/2025 · Authority · 2025-02-27
HighK-RERAOpen