Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.
Snapshot 12 Oct 2026. Check rera.kerala.gov.in.
Wayanad · 2021 · K-RERA/PRJ/059/2021
Wayanad · 2021 · K-RERA/PRJ/WYD/083/2021
Same cohort: Wayanad · 2021.
Project
CHILGROVE
KUNNATHIDAVAKA, Wayanad
THE KALLAT PEARL PHASE-1
THOMATTUCHAL, Wayanad
Promised date
04 Jun 2023
no date change on file
31 Dec 2024
20 months past promised date
Physical %
100%
filed 05 Oct 2023
64%
filed 30 Apr 2023
Booked %
88%
21 of 24
61%
46 of 75
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 07 Jul 2025 · 423d ago · Stale
Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.