THE KALLAT PEARL PHASE-1

Overdue

KALLAT PEARL BUILDERS LLP · Villas · THOMATTUCHAL, Wayanad · K-RERA/PRJ/WYD/083/2021

Physical progress
64%
filed 30 Apr 2023
Proposed completion
31 Dec 2024
20 months past
Units booked
61%
46 of 75
Quarterly update
Stale
Q1 2025 · filed 07 Jul 2025 · 423d ago

As filed with K-RERA

Registration
K-RERA/PRJ/WYD/083/2021
granted 24 Dec 2021
Promoter
KALLAT PEARL BUILDERS LLP
Location
THOMATTUCHAL, Wayanad, 673592
Type
Villas
75 building(s)
Plot area
17,667 sqm
Registered floor area
3,805 sqm
≈ 40,957 sqft · residential 3,805 sqm · other 0 sqm
Units
75
75 residential · 40 plots
Project start
—
Proposed completion
31 Dec 2024
Extension
—
Physical progress
64%
Financial progress
64%
Escrow bank
STATE BANK OF INDIA
Financier
NIL
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

4 of 5 filed
Architect Form 2
latest 29 Nov 2025
filed
Engineer Form 3
latest 29 Nov 2025
filed
CA Form 4
latest 29 Nov 2025
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
on file
filed

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Same district, same year

Form 5 · statement of accounts

4 of 4 open on K-RERA
Collected FY 2024–25
₹76.1 L
₹76,10,517 as filed
Deposited
₹53.3 L
70.0% of collected
Withdrawn
₹52.1 L
from the separate account
Closing (year-end)
₹7.0 L
FY 2024–25 closing — not today’s balance
Separate account

FY 2024–25 Form 5 · as filed 29 Nov 2025 · read via OCR · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹5,84,444
Collected from allottees
₹76,10,517
Deposited in separate account
70.0% of collected
₹53,27,362
Withdrawn
₹52,11,479
Closing
₹7,00,327
withdrawn ₹52,11,479year-end leftover ₹7,00,327

Closing is 11.8% of money that went through the separate account (opening + deposited). 70.0% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

FY 2024–25
filed 29 Nov 2025 · file 183871
₹76,10,517 in
FY 2023–24
filed 07 Nov 2024 · file 138525
₹1,44,68,749 in
Filed 07 Jun 2023
file 90045
PDF on K-RERA · not parsed
FY 2021–22
filed 31 Oct 2022 · file 75250
₹77,98,977 in

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

2 from register
TypeSignalSeveritySourceStatus
R
20 months past proposed completion
↳ Proposed 2024-12-31, physical progress 64%
HighK-RERAOpen
D
Quarterly update is stale
↳ Last filed 2025-07-07 (Q1 2025)
LowK-RERAOpen