Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2023 · K-RERA/PRJ/ERN/217/2023

Ernakulam · 2023 · K-RERA/PRJ/ERN/193/2023

Same cohort: Ernakulam · 2023.

As filed
ASIAN ALLEGRACompleted
Project
ASIAN ALLEGRA
MARADU, Ernakulam
FERN KENSINGTON
MARADU, Ernakulam
Promised date
05 Sept 2023
no date change on file
30 Nov 2027
no date change on file
Physical %
100%
filed 08 Nov 2023
30%
not filed
Booked %
100%
16 of 16
99%
110 of 111
Complaints
3
1 final order
13
3 final orders
Last QPR
N/A
closed on the register — QPR not expected
Q1 2025
filed 18 Jul 2025 · 412d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.