Skip to main content
Enthayi?
K-RERA
← Projects

Compare

Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2023 · K-RERA/PRJ/ERN/196/2023

Ernakulam · 2023 · K-RERA/PRJ/ERN/193/2023

Same cohort: Ernakulam · 2023.

As filed
ASSET SREYASOn Track
Project
ASSET SREYAS
CHERANALLUR, Ernakulam
FERN KENSINGTON
MARADU, Ernakulam
Promised date
12 Mar 2028
no date change on file
30 Nov 2027
no date change on file
Physical %
30%
not filed
30%
not filed
Booked %
59%
44 of 74
99%
110 of 111
Complaints
none on file
from the public complaints list
13
3 final orders
Last QPR
Q2 2026
filed 06 Oct 2026 · -33d ago · Current
Q1 2025
filed 18 Jul 2025 · 412d ago · Stale

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.