Same district, same year — promised date, physical %, booked %, complaints, last QPR. As filed. Not a ranking.

Snapshot 12 Oct 2026. Check rera.kerala.gov.in.

Ernakulam · 2021 · K-RERA/PRJ/155/2021

Ernakulam · 2021 · K-RERA/PRJ/ERN/005/2021

Same cohort: Ernakulam · 2021.

As filed
Eco OneOverdue
Project
TREESA GARDENS
EDAPPALLY SOUTH, Ernakulam
Eco One
AIKARANAD SOUTH, Ernakulam
Promised date
28 Feb 2025
18 months past promised date
31 Jul 2024
25 months past promised date
Physical %
94%
filed 29 Jul 2023
79%
not filed
Booked %
100%
12 of 6
88%
15 of 17
Complaints
none on file
from the public complaints list
none on file
from the public complaints list
Last QPR
Q3 2024
filed 07 Jan 2025 · 604d ago · Stale
Q2 2026
filed 07 Oct 2026 · -34d ago · Current

Dash means missing on the snapshot. Status is derived from filed dates. Check rera.kerala.gov.in.