Kalyan Developers

Portfolio of 19 registered projects · Thrissur, Thiruvananthapuram, Ernakulam, Kozhikode · register read 12 Oct 2026

Projects
19
11 completed
Active
8
Overdue
1
past promised date
Complaints · cases
5 · 0
QPR current
88%
active projects filed in 120d
Units booked
74%
866 of 1,171 · 247k sqm

Status mix

Quarterly filing discipline

Projects

sorted by promised completion

RAID

7 from register
TypeProjectSignalSeveritySourceStatus
IKalyan Avanti
Kalyan Developers
1 complaint filed with K-RERA, 1 final order
↳ Latest 25/2023 · Authority · 2023-06-13
HighK-RERAOpen
IKalyan Marvella
Kalyan Developers
4 complaints filed with K-RERA, 1 final order
↳ Latest 21/2022 · Authority · 2025-08-01
HighK-RERAOpen
RKalyan Prima
Kalyan Developers
8 months past proposed completion
↳ Proposed 2025-12-31, physical progress 89%
MediumK-RERAOpen
RKalyan Heritage
Kalyan Developers
Completion date moved by 6 months
↳ 2021-06-30 → 2021-12-30
MediumK-RERAOpen
RKalyan Credenz
Kalyan Developers
Completion date moved by 6 months
↳ 2022-12-31 → 2023-06-30
MediumK-RERAOpen
RKalyan Sapphire
Kalyan Developers
Completion date moved by 6 months
↳ 2020-10-15 → 2021-04-15
MediumK-RERAOpen
DKalyan Prima
Kalyan Developers
Quarterly update is stale
↳ Last filed 2025-10-06 (Q2 2025)
LowK-RERAOpen