M/s Skyline Builders
Portfolio of 31 registered projects · Kozhikode, Ernakulam, Thrissur, Pathanamthitta, Kottayam, Kannur, Thiruvananthapuram · register read 12 Oct 2026
Projects
31
19 completed
Active
12
Overdue
1
past promised date
Complaints · cases
2 · 1
QPR current
92%
active projects filed in 120d
Units booked
83%
1,413 of 1,712 · 325k sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
14 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| I | SKYLINE PEARL M/s Skyline Builders | 1 complaint filed with K-RERA, 1 final order ↳ Latest 164/2024 · Authority · 2024-10-10 | High | K-RERA | Open |
| I | SKYLINE MATRIX M/s Skyline Builders | Legal case listed on the register | High | K-RERA | Open |
| I | SKYLINE MATRIX M/s Skyline Builders | 1 complaint filed with K-RERA, 1 final order ↳ Latest 126/2023 · Authority · 2023-07-19 | High | K-RERA | Open |
| R | SKYLINE BLUE VISTA M/s Skyline Builders | Completion date moved by 6 months ↳ 2022-11-30 → 2023-05-30 | Medium | K-RERA | Open |
| R | SKYLINE ARISTOCRAT M/s Skyline Builders | Completion date moved by 6 months ↳ 2021-06-28 → 2021-12-28 | Medium | K-RERA | Open |
| R | SKYLINE POLARIS M/s Skyline Builders | Completion date moved by 6 months ↳ 2023-07-31 → 2024-01-31 | Medium | K-RERA | Open |
| R | SKYLINE EPIC M/s Skyline Builders | Completion date moved by 6 months ↳ 2022-04-30 → 2022-10-30 | Medium | K-RERA | Open |
| R | SKYLINE AVENUE SUITES M/s Skyline Builders | Completion date moved by 6 months ↳ 2023-01-30 → 2023-07-30 | Medium | K-RERA | Open |
| R | SKYLINE WINDMILL M/s Skyline Builders | Completion date moved by 6 months ↳ 2024-01-30 → 2024-07-30 | Medium | K-RERA | Open |
| R | SKYLINE PEARL M/s Skyline Builders | Completion date moved by 6 months ↳ 2024-03-31 → 2024-09-30 | Medium | K-RERA | Open |
| R | SKYLINE SANCTUARY M/s Skyline Builders | 10 months past proposed completion ↳ Proposed 2025-10-30, physical progress 98% | Medium | K-RERA | Open |
| A | SKYLINE DYNASTY M/s Skyline Builders | Spend running ahead of build ↳ Financial 35% vs physical 12% | Medium | K-RERA | Open |
| A | SKYLINE URBAN OASIS 2 M/s Skyline Builders | Spend running ahead of build ↳ Financial 40% vs physical 4% | Medium | K-RERA | Open |
| D | SKYLINE SANCTUARY M/s Skyline Builders | Quarterly update is stale ↳ Last filed 2025-09-02 (Q2 2025) | Low | K-RERA | Open |