MERITRA HOMES PVT LTD
Portfolio of 8 registered projects · Ernakulam · register read 12 Oct 2026
Projects
8
3 completed
Active
5
Overdue
1
past promised date
Complaints · cases
0 · 1
QPR current
80%
active projects filed in 120d
Units booked
62%
182 of 293 · 55,913 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
5 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | ATMOSPHERE MERITRA HOMES PVT LTD | Completion date moved by 18 months ↳ 2023-09-30 → 2025-03-31 | High | K-RERA | Open |
| R | ATMOSPHERE MERITRA HOMES PVT LTD | 17 months past proposed completion ↳ Proposed 2025-03-31, physical progress 78% | High | K-RERA | Open |
| I | RAINWOODS MERITRA HOMES PVT LTD | Legal case listed on the register | High | K-RERA | Open |
| R | RAINWOODS MERITRA HOMES PVT LTD | Completion date moved by 6 months ↳ 2022-10-25 → 2023-04-24 | Medium | K-RERA | Open |
| D | ATMOSPHERE MERITRA HOMES PVT LTD | Quarterly update is stale ↳ Last filed 2025-01-07 (Q3 2024) | Low | K-RERA | Open |