← Promoters
Green Vistas Infrastructure Projects
Portfolio of 1 registered project · Ernakulam · register read 12 Oct 2026
Projects
1
0 completed
Active
1
Overdue
1
past promised date
Complaints · cases
0 · 0
QPR current
100%
active projects filed in 120d
Units booked
29%
29 of 99 · 11,781 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
2 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | Prakrriti-Block4 Green Vistas Infrastructure Projects | Completion date moved by 12 months ↳ 2024-12-31 → 2025-12-30 | Medium | K-RERA | Open |
| R | Prakrriti-Block4 Green Vistas Infrastructure Projects | 8 months past proposed completion ↳ Proposed 2025-12-30, physical progress 68% | Medium | K-RERA | Open |