← Promoters
DEODATE ENVIRONMENTAL HOMES PVT LTD
Portfolio of 3 registered projects · Thiruvananthapuram · register read 12 Oct 2026
Projects
3
1 completed
Active
2
Overdue
1
past promised date
Complaints · cases
0 · 0
QPR current
50%
active projects filed in 120d
Units booked
49%
22 of 45 · 7,240 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
3 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | DEODATE PRAYAGA DEODATE ENVIRONMENTAL HOMES PVT LTD | 37 months past proposed completion ↳ Proposed 2023-08-23, physical progress 0% | High | K-RERA | Open |
| A | DEODATE MERCEDES DEODATE ENVIRONMENTAL HOMES PVT LTD | Spend running ahead of build ↳ Financial 90% vs physical 0% | Medium | K-RERA | Open |