GALAXY HOMES PVT LTD
Portfolio of 9 registered projects · Ernakulam · register read 12 Oct 2026
Projects
9
5 completed
Active
4
Overdue
4
past promised date
Complaints · cases
82 · 1
QPR current
0%
active projects filed in 120d
Units booked
92%
664 of 724 · 64,808 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
17 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| I | GALAXY EMERALD GALAXY HOMES PVT LTD | Legal case listed on the register | High | K-RERA | Open |
| I | GALAXY EMERALD GALAXY HOMES PVT LTD | 9 complaints filed with K-RERA, 6 final orders ↳ Latest 104/2026 · Authority · 2026-08-31 | High | K-RERA | Open |
| R | GALAXY EMERALD GALAXY HOMES PVT LTD | 46 months past proposed completion ↳ Proposed 2022-11-19, physical progress 85% | High | K-RERA | Open |
| I | GALAXY BRIDGEWOOD GALAXY HOMES PVT LTD | 10 complaints filed with K-RERA, 3 final orders ↳ Latest 159/2025 · Authority · 2025-11-01 | High | K-RERA | Open |
| R | GALAXY BRIDGEWOOD GALAXY HOMES PVT LTD | 48 months past proposed completion ↳ Proposed 2022-09-30, physical progress 95% | High | K-RERA | Open |
| I | GALAXY MIDWINTER GALAXY HOMES PVT LTD | 6 complaints filed with K-RERA, 4 final orders ↳ Latest 64/2023 · Authority · 2023-04-03 | High | K-RERA | Open |
| I | GALAXY CARLTON GALAXY HOMES PVT LTD | 7 complaints filed with K-RERA, 2 final orders ↳ Latest 123/2024 · Authority · 2024-08-08 | High | K-RERA | Open |
| I | GALAXY GOLDENDALE GALAXY HOMES PVT LTD | 6 complaints filed with K-RERA, 5 final orders ↳ Latest 35/2024 · Authority · 2024-04-01 | High | K-RERA | Open |
| R | GALAXY GOLDENDALE GALAXY HOMES PVT LTD | 43 months past proposed completion ↳ Proposed 2023-02-11, physical progress 95% | High | K-RERA | Open |
| I | GALAXY PINE COURT BLOCK I GALAXY HOMES PVT LTD | 11 complaints filed with K-RERA, 5 final orders ↳ Latest 34/2025 · Authority · 2025-02-28 | High | K-RERA | Open |
| R | GALAXY PINE COURT BLOCK I GALAXY HOMES PVT LTD | 49 months past proposed completion ↳ Proposed 2022-08-22, physical progress 95% | High | K-RERA | Open |
| I | GALAXY CLOUDSPACE GALAXY HOMES PVT LTD | 27 complaints filed with K-RERA, 20 final orders ↳ Latest 76/2023 · Authority · 2023-04-26 | High | K-RERA | Open |
| I | GALAXY OXTON GALAXY HOMES PVT LTD | 6 complaints filed with K-RERA, 4 final orders ↳ Latest 154/2024 · Authority · 2024-09-24 | High | K-RERA | Open |
| D | GALAXY EMERALD GALAXY HOMES PVT LTD | Quarterly update is stale ↳ Last filed 2025-07-02 (Q1 2025) | Low | K-RERA | Open |
| D | GALAXY BRIDGEWOOD GALAXY HOMES PVT LTD | Quarterly update is stale ↳ Last filed 2025-07-02 (Q1 2025) | Low | K-RERA | Open |
| D | GALAXY GOLDENDALE GALAXY HOMES PVT LTD | Quarterly update is stale ↳ Last filed 2025-07-02 (Q1 2025) | Low | K-RERA | Open |
| D | GALAXY PINE COURT BLOCK I GALAXY HOMES PVT LTD | Quarterly update is stale ↳ Last filed 2025-10-02 (Q2 2025) | Low | K-RERA | Open |