Confident Projects Residential
Portfolio of 49 registered projects · Thiruvananthapuram, Kozhikode, Ernakulam, Kottayam, Thrissur, Malappuram · register read 12 Oct 2026
Projects
49
23 completed
Active
26
Overdue
1
past promised date
Complaints · cases
0 · 1
QPR current
96%
active projects filed in 120d
Units booked
78%
3,771 of 4,854 · 606k sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
16 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | CONFIDENT GREENFIELD Confident Projects Residential | Completion date moved by 20 months ↳ 2023-05-12 → 2025-01-10 | High | K-RERA | Open |
| R | CONFIDENT ZENITH Confident Projects Residential | Completion date moved by 24 months ↳ 2023-03-01 → 2025-03-01 | High | K-RERA | Open |
| R | CONFIDENT BLUEBERRY Confident Projects Residential | Completion date moved by 24 months ↳ 2023-02-15 → 2025-02-15 | High | K-RERA | Open |
| I | CONFIDENT FAIRFIELD Confident Projects Residential | Legal case listed on the register | High | K-RERA | Open |
| R | CONFIDENT FLORIS Confident Projects Residential | Completion date moved by 6 months ↳ 2020-04-20 → 2020-10-20 | Medium | K-RERA | Open |
| R | CONFIDENT DAFFODILS BLOCK A and B Confident Projects Residential | Completion date moved by 6 months ↳ 2020-11-01 → 2021-05-01 | Medium | K-RERA | Open |
| R | GARDENIA Confident Projects Residential | Completion date moved by 6 months ↳ 2020-09-30 → 2021-03-30 | Medium | K-RERA | Open |
| R | Confident White Berry Confident Projects Residential | 10 months past proposed completion ↳ Proposed 2025-11-01, physical progress 88% | Medium | K-RERA | Open |
| A | Confident white House Confident Projects Residential | Spend running ahead of build ↳ Financial 93% vs physical 70% | Medium | K-RERA | Open |
| A | CONFIDENT EBONY, THRISSUR Confident Projects Residential | Spend running ahead of build ↳ Financial 100% vs physical 69% | Medium | K-RERA | Open |
| A | CONFIDENT PINEWOOD Confident Projects Residential | Spend running ahead of build ↳ Financial 99% vs physical 79% | Medium | K-RERA | Open |
| A | CONFIDENT BOUGAINVILLE Confident Projects Residential | Spend running ahead of build ↳ Financial 100% vs physical 75% | Medium | K-RERA | Open |
| A | CONFIDENT OASIS Confident Projects Residential | Spend running ahead of build ↳ Financial 96% vs physical 65% | Medium | K-RERA | Open |
| A | CONFIDENT SUNFLOWER Confident Projects Residential | Spend running ahead of build ↳ Financial 86% vs physical 65% | Medium | K-RERA | Open |
| A | CONFIDENT FAIRFIELD Confident Projects Residential | Spend running ahead of build ↳ Financial 65% vs physical 44% | Medium | K-RERA | Open |
| D | Confident White Berry Confident Projects Residential | Quarterly update is stale ↳ Last filed 2025-10-06 (Q2 2025) | Low | K-RERA | Open |