Nizwa Property Developers
Portfolio of 1 registered project · Thiruvananthapuram · register read 12 Oct 2026
Projects
1
0 completed
Active
1
Overdue
1
past promised date
Complaints · cases
0 · 0
QPR current
0%
active projects filed in 120d
Units booked
0%
0 of 28 · 2,578 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
2 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | ECLAT TOWER Nizwa Property Developers | 48 months past proposed completion ↳ Proposed 2022-09-30, physical progress 0% | High | K-RERA | Open |
| D | ECLAT TOWER Nizwa Property Developers | Quarterly update is stale ↳ Last filed 2024-01-09 (Q4 2023) | Low | K-RERA | Open |