Nizwa Property Developers

Portfolio of 1 registered project · Thiruvananthapuram · register read 12 Oct 2026

Projects
1
0 completed
Active
1
Overdue
1
past promised date
Complaints · cases
0 · 0
QPR current
0%
active projects filed in 120d
Units booked
0%
0 of 28 · 2,578 sqm

Status mix

Quarterly filing discipline

Projects

sorted by promised completion

RAID

2 from register
TypeProjectSignalSeveritySourceStatus
RECLAT TOWER
Nizwa Property Developers
48 months past proposed completion
↳ Proposed 2022-09-30, physical progress 0%
HighK-RERAOpen
DECLAT TOWER
Nizwa Property Developers
Quarterly update is stale
↳ Last filed 2024-01-09 (Q4 2023)
LowK-RERAOpen