ACCORD HABITAT PRIVATE LIMITED
Portfolio of 2 registered projects · Ernakulam · register read 12 Oct 2026
Projects
2
1 completed
Active
1
Overdue
0
past promised date
Complaints · cases
0 · 0
QPR current
100%
active projects filed in 120d
Units booked
33%
15 of 46 · 7,073 sqm
Status mix
Quarterly filing discipline
Projects
sorted by promised completion
RAID
2 from register
| Type | Project | Signal | Severity | Source | Status |
|---|---|---|---|---|---|
| R | ACCORD FERRY BAY ACCORD HABITAT PRIVATE LIMITED | Completion date moved by 6 months ↳ 2023-12-31 → 2024-06-30 | Medium | K-RERA | Open |
| A | ACCORD SOVEREIGN ACCORD HABITAT PRIVATE LIMITED | Spend running ahead of build ↳ Financial 23% vs physical 1% | Medium | K-RERA | Open |