Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
Jayaraj Divya
CompletedStatus is from the dates they filed. Not a court finding.
Building
Jayaraj Divya
Who is building it
Jayaraj Properties
Official number
K-RERA/PRJ/078/2020 · 26 May 2021
Where
PALAKKAD-2, Palakkad, 678001
Type
Apartments
Promised ready date
30 Jun 2023
they changed it from 31 Dec 2022
How much they say is done
100%
they have not filed how much is done
How many already sold
16 of 16
100% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
16
Booked count
16
Escrow bank
HDFC
Legal case
No
Form 5 · FY 2020–21
Rupees only where the ledger balanced on extract. Filed 29 Oct 2022. Read via OCR.
Collected
₹1,66,04,427
Deposited
₹1,66,04,427 · 100.0% of collected
Withdrawn
₹1,65,65,000
Closing
₹43,835 · year-end, not today