SKP Tower

On Track

· Apartments · NADAMA, Ernakulam · K-RERA/PRJ/247/2020

Physical progress
99%
listing 99% · folder 94%
Proposed completion
05 Nov 2026
moved +22 mo from 05 Jan 2025
Units booked
0%
0 of 32
Quarterly update
Current
Q2 2026 · filed 04 Oct 2026 · -31d ago

As filed with K-RERA

Registration
K-RERA/PRJ/247/2020
granted 05 May 2021
Promoter
—
Location
NADAMA, Ernakulam, 682301
Type
Apartments
1 building(s)
Plot area
769 sqm
Registered floor area
4,281 sqm
≈ 46,085 sqft · residential 3,975 sqm · other 211 sqm
Units
32
31 residential · 1 commercial
Project start
—
Proposed completion
05 Nov 2026
previously 05 Jan 2025
Extension
—
Physical progress
99%
Financial progress
99%
Escrow bank
The Federal bank Limited
Financier
Federal Bank
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

1 of 5 filed
Architect Form 2
unable to find
not found
Engineer Form 3
unable to find
not found
CA Form 4
latest 05 Oct 2023
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

6 of 6 open on K-RERA
Filed 05 Nov 2025
file 182022
PDF on K-RERA · not parsed
Filed 05 Nov 2025
file 182023
PDF on K-RERA · not parsed
Filed 05 Nov 2025
file 182024
PDF on K-RERA · not parsed
Filed 03 Oct 2024
file 134580
PDF on K-RERA · not parsed
Filed 05 Oct 2023
file 98509
PDF on K-RERA · not parsed
Filed 27 Oct 2022
file 74816
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

1 from register
TypeSignalSeveritySourceStatus
R
Completion date moved by 22 months
↳ 2025-01-05 → 2026-11-05
HighK-RERAOpen