Sparrow Paradisia

Overdue1 complaint · 1 order

Sparrow Construction Management and Consultancy · Apartments · KUDAPPANAKUNNU, Thiruvananthapuram · K-RERA/PRJ/TVM/038/2022

Physical progress
97%
filed 24 Oct 2023
Proposed completion
28 Feb 2023
43 months past
Units booked
78%
14 of 18
Quarterly update
Stale
Q1 2025 · filed 09 Jul 2025 · 421d ago

As filed with K-RERA

Registration
K-RERA/PRJ/TVM/038/2022
granted 10 Mar 2022
Promoter
Sparrow Construction Management and Consultancy
Location
KUDAPPANAKUNNU, Thiruvananthapuram, 695005
Type
Apartments
1 building(s)
Plot area
953 sqm
Registered floor area
4,346 sqm
≈ 46,775 sqft · residential 3,492 sqm · other 853 sqm
Units
18
16 residential · 2 commercial
Project start
—
Proposed completion
28 Feb 2023
Extension
—
Physical progress
97%
Financial progress
90%
Escrow bank
Axis Bank
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

0 of 5 filed
Architect Form 2
unable to find
not found
Engineer Form 3
unable to find
not found
CA Form 4
unable to find
not found
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

2 of 2 open on K-RERA
Filed 21 Jan 2023
file 81961
PDF on K-RERA · not parsed
Filed 21 Jan 2023
file 81962
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

1 of 1 decided
177/2023final order
M/s Sparrow Construction
Authority19 Oct 2023

RAID

3 from register
TypeSignalSeveritySourceStatus
I
1 complaint filed with K-RERA, 1 final order
↳ Latest 177/2023 · Authority · 2023-10-19
HighK-RERAOpen
R
43 months past proposed completion
↳ Proposed 2023-02-28, physical progress 97%
HighK-RERAOpen
D
Quarterly update is stale
↳ Last filed 2025-07-09 (Q1 2025)
LowK-RERAOpen