As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
VARMA CONNEKT
OverdueStatus is from the dates they filed. Not a court finding.
Building
VARMA CONNEKT
Who is building it
VARMA HOMES PRIVATE LIMITED
Official number
K-RERA/PRJ/ERN/014/2021 · 15 May 2021
Where
EDAPPALLY SOUTH, Ernakulam, 682028
Type
Apartments
Promised ready date
01 Dec 2025
9 months past this date · they did not change it on file
How much they say is done
98%
this is what they filed on 04 Dec 2023
How many already sold
20 of 27
74% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
Q2 2025
sent 06 Oct 2025
On the register
Units
27
Booked count
20
Escrow bank
THE SOUTH INDIAN BANK
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 27 Oct 2025. Read via OCR.
Collected
₹9,58,18,496
Deposited
₹9,58,18,496 · 100.0% of collected
Withdrawn
₹9,56,86,940
Closing
₹5,47,127 · year-end, not today