Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
Sobha Atlantis Phase 1 block 3 and 4
On TrackStatus is from the dates they filed. Not a court finding.
Building
Sobha Atlantis Phase 1 block 3 and 4
Who is building it
Sobha Limited
Official number
K-RERA/PRJ/235/2020 · 18 Sept 2021
Where
NADAMA, Ernakulam, 682019
Type
Apartments
Promised ready date
30 Oct 2026
they did not change this date on file
How much they say is done
98%
this is what they filed on 07 Oct 2023
How many already sold
154 of 192
80% flats sold
Complaints
none on file
a legal case is marked on the register
Last update to K-RERA
Q2 2026
sent 07 Oct 2026
On the register
Units
192
Booked count
154
Escrow bank
Andhra bank
Legal case
Yes
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 31 Oct 2025.
Collected
₹86,06,71,714
Deposited
₹60,24,70,200 · 70.0% of collected
Withdrawn
₹58,58,95,011
Closing
₹1,65,93,154 · year-end, not today