SKY CITY VILLAS

Overdue3 complaints · 1 order

INDUS GRATIA CREATIVE HOMES PVT LTD · Villas · KUNNATHUNAD, Ernakulam · K-RERA/PRJ/ERN/011/2021

Physical progress
70%
not filed
Proposed completion
04 Aug 2026
1 months past
Units booked
100%
32 of 1
Quarterly update
Current
Q1 2026 · filed 10 Jul 2026 · 55d ago

As filed with K-RERA

Registration
K-RERA/PRJ/ERN/011/2021
granted 05 May 2021
Promoter
INDUS GRATIA CREATIVE HOMES PVT LTD
Location
KUNNATHUNAD, Ernakulam, 683565
Type
Villas
1 building(s)
Plot area
4,486 sqm
Registered floor area
157 sqm
≈ 1,686 sqft · residential 157 sqm · other 0 sqm
Units
1
1 residential · 19 plots
Project start
05 Apr 2021
Proposed completion
04 Aug 2026
Extension
—
Physical progress
70%
Common area works of electrical and road work completed. Two villa works in progress(one Tile work and first floor lintel work in progress)
Financial progress
69%
Proportion of the cost incurred and paid on Land cost and construction cost to the total estimated cost
Escrow bank
SOUTH INDIAN BANK
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 11 Jul 2026
filed
Engineer Form 3
latest 11 Jul 2026
filed
CA Form 4
latest 10 Jul 2026
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

5 of 5 open on K-RERA
Filed 18 Nov 2025
file 182845
PDF on K-RERA · not parsed
Filed 09 Dec 2024
file 140828
PDF on K-RERA · not parsed
Filed 14 Nov 2023
file 102338
PDF on K-RERA · not parsed
Filed 05 Dec 2022
file 77837
PDF on K-RERA · not parsed
Filed 31 Mar 2022
file 51477
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

1 of 3 decided
12/2026pending
M/s Indusgratia Creative Homes Pvt Ltd and Other
Authority13 Feb 2026
35/2024final order
M/s Indusgratia creative Homes and another
Adjudicating Officer04 Jan 2025
217/2024pending
M/s Indusgratia Creative Homes Pvt Ltd & Other
Authority21 Dec 2024

RAID

2 from register
TypeSignalSeveritySourceStatus
I
3 complaints filed with K-RERA, 1 final order
↳ Latest 12/2026 · Authority · 2026-02-13
HighK-RERAOpen
R
1 months past proposed completion
↳ Proposed 2026-08-04, physical progress 70%
MediumK-RERAOpen