ASTEN NAUTICA

Overdue

Status is from the dates they filed. Not a court finding.

Building
ASTEN NAUTICA
Who is building it
ASTEN REALTORS PRIVATE LIMITED
Official number
K-RERA/PRJ/102/2021 · 17 Apr 2021
Where
KUMBALAM, Ernakulam, 682506
Type
Apartments
Promised ready date
30 Dec 2025
they changed it from 30 Jun 2025 · 8 months past
How much they say is done
0%
they have not filed how much is done
How many already sold
0 of 64
0% flats sold
Complaints
6
2 already decided
Last update to K-RERA
Q3 2024
sent 07 Jan 2025

On the register

Units
64
Booked count
0
Escrow bank
THE SOUTH INDIAN BANK
Legal case
No

Form 5 · FY 2021–22

Rupees only where the ledger balanced on extract. Filed 31 Oct 2022. Read via OCR.

Collected
₹50,00,000
Deposited
₹50,00,000 · 100.0% of collected
Withdrawn
₹50,00,000
Closing
₹0 · year-end, not today

Complaints before K-RERA · 6

193/2022 · Authority
final order
249/2021 · Authority
pending
157/2021 · Adjudicating Officer
final order
136/2021 · Adjudicating Officer
pending
135/2021 · Adjudicating Officer
pending
134/2021 · Adjudicating Officer
pending

Copied from public Kerala RERA filings. Independent. Not K-RERA. Not legal advice. Status is derived from filed dates and percents. Dash means missing on this snapshot. Documents stay on the portal — we link, we do not host.

Check rera.kerala.gov.in · this project folder · live page.