Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
TRINITY ACCORD
CompletedStatus is from the dates they filed. Not a court finding.
Building
TRINITY ACCORD
Who is building it
TRINITY ARCADE PVT LTD
Official number
K-RERA/PRJ/201/2020 · 30 Apr 2021
Where
EDAPPALLY SOUTH, Ernakulam, 682024
Type
Apartments
Promised ready date
30 Jun 2025
they did not change this date on file
How much they say is done
100%
this is what they filed on 25 Nov 2023
How many already sold
44 of 59
75% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
59
Booked count
44
Escrow bank
State Bank Of India
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 03 Dec 2025. Read via OCR.
Collected
₹23,41,77,807
Deposited
₹16,39,24,465 · 70.0% of collected
Withdrawn
₹16,50,65,141
Closing
₹0 · year-end, not today