Snapshot 12 Oct 2026

Check rera.kerala.gov.in

ANTA - CAPITAL GREEN

Overdue

Status is from the dates they filed. Not a court finding.

Building
ANTA - CAPITAL GREEN
Who is building it
ANTA BUILDERS & DEVELOPERS PVT LTD
Official number
K-RERA/PRJ/248/2020 · 15 Jul 2021
Where
VEGANOOR, Thiruvananthapuram, 682311
Type
Villas
Promised ready date
30 Oct 2024
they changed it from 30 Apr 2024 · 22 months past
How much they say is done
93%
they have not filed how much is done
How many already sold
38 of 38
100% flats sold
Complaints
2
1 already decided
Last update to K-RERA
Q3 2024
sent 21 Jan 2025

On the register

Units
38
Booked count
38
Escrow bank
STATE BANK OF INDIA
Legal case
No

Form 5 · FY 2023–24

Rupees only where the ledger balanced on extract. Filed 31 Oct 2024. Read via OCR.

Collected
₹2,72,71,887
Deposited
₹2,72,71,887 · 100.0% of collected
Withdrawn
₹2,72,71,092
Closing
₹3,974 · year-end, not today

Complaints before K-RERA · 2

75/2024 · Authority
pending
07/2023 · Authority
final order

Copied from public Kerala RERA filings. Independent. Not K-RERA. Not legal advice. Status is derived from filed dates and percents. Dash means missing on this snapshot. Documents stay on the portal — we link, we do not host.