Marina One Phase 3

On Track

Status is from the dates they filed. Not a court finding.

Building
Marina One Phase 3
Who is building it
Sobha Limited
Official number
K-RERA/PRJ/253/2020 · 01 Sept 2021
Where
ERNAKULAM, Ernakulam, 682018
Type
Apartments
Promised ready date
30 Oct 2027
they did not change this date on file
How much they say is done
87%
this is what they filed on 07 Oct 2023
How many already sold
177 of 181
98% flats sold
Complaints
none on file
a legal case is marked on the register
Last update to K-RERA
Q2 2026
sent 07 Oct 2026

On the register

Units
181
Booked count
177
Escrow bank
ICICI
Legal case
Yes

Form 5 · FY 2024–25

Rupees only where the ledger balanced on extract. Filed 30 Oct 2025.

Collected
₹72,69,10,927
Deposited
₹50,88,37,649 · 70.0% of collected
Withdrawn
₹50,80,89,000
Closing
₹14,76,507 · year-end, not today

Copied from public Kerala RERA filings. Independent. Not K-RERA. Not legal advice. Status is derived from filed dates and percents. Dash means missing on this snapshot. Documents stay on the portal — we link, we do not host.