Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
Kalyan Marvella
CompletedStatus is from the dates they filed. Not a court finding.
Building
Kalyan Marvella
Who is building it
Kalyan Developers
Official number
K-RERA/PRJ/155/2020 · 19 Jul 2021
Where
ERNAKULAM, Ernakulam, 682020
Type
Apartments
Promised ready date
30 Sept 2021
they did not change this date on file
How much they say is done
100%
this is what they filed on 05 Jan 2023
How many already sold
34 of 36
94% flats sold
Complaints
4
1 already decided
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
36
Booked count
34
Escrow bank
HDFC
Legal case
No
Form 5 · FY 2021–22
Rupees only where the ledger balanced on extract. Filed 25 Oct 2022. Read via OCR.
Collected
₹1,56,00,150
Deposited
₹1,56,00,150 · 100.0% of collected
Withdrawn
₹1,26,87,433
Closing
₹31,76,343 · year-end, not today
Complaints before K-RERA · 4
21/2022 · Authority
pending
208/2024 · Authority
pending
206/2024 · Authority
pending
72/2024 · Authority
final order