On Track

· Villas · VEMBAYAM, Thiruvananthapuram · K-RERA/PRJ/TVM/105/2026

Physical progress
14%
not filed
Proposed completion
30 Apr 2032
no date change on file
Units booked
4%
1 of 24
Quarterly update
Current
Q2 2026 · filed 06 Oct 2026 · -33d ago

As filed with K-RERA

Registration
K-RERA/PRJ/TVM/105/2026
granted 15 Jul 2026
Promoter
—
Location
VEMBAYAM, Thiruvananthapuram, 695584
Type
Villas
24 building(s)
Plot area
8,553 sqm
Registered floor area
5,752 sqm
≈ 61,911 sqft · residential 5,560 sqm · other 191 sqm
Units
24
23 residential · 1 commercial · 23 plots
Project start
15 Apr 2026
Proposed completion
30 Apr 2032
Extension
—
Physical progress
14%
Phsical Progress
Financial progress
11%
Financial Progress
Escrow bank
SOUTH INDIAN BANK
Financier
Not applicable
Complaint
No
Legal case
No
Authority order
No

Folder noticeboard

0 of 5 filed
Architect Form 2
unable to find
not found
Engineer Form 3
unable to find
not found
CA Form 4
unable to find
not found
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

No Form 5 on the public noticeboard for this project. That is also a fact.

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

0 from register
No rows from the register.