As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
NAVERA ANTALYA
On TrackStatus is from the dates they filed. Not a court finding.
Building
NAVERA ANTALYA
Who is building it
Navera Builders Private Limited
Official number
K-RERA/PRJ/TSR/027/2025 · 11 Feb 2025
Where
NADATHARA, Thrissur, 680751
Type
Apartments
Promised ready date
30 Apr 2031
they did not change this date on file
How much they say is done
8%
they have not filed how much is done
How many already sold
32 of 56
57% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
Q2 2026
sent 06 Oct 2026
On the register
Units
56
Booked count
32
Escrow bank
HDFC BANK
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 29 Oct 2025.
Collected
₹55,57,384
Deposited
₹28,32,961 · 51.0% of collected
Withdrawn
₹28,32,961
Closing
₹0 · year-end, not today