Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
CONFIDENT GATEWAY
On TrackStatus is from the dates they filed. Not a court finding.
Building
CONFIDENT GATEWAY
Who is building it
Confident Projects Residential
Official number
K-RERA/PRJ/ERN/074/2024 · 12 Apr 2024
Where
KAKKANAD, Ernakulam, 682039
Type
Apartments
Promised ready date
02 Sept 2029
they did not change this date on file
How much they say is done
22%
they have not filed how much is done
How many already sold
72 of 100
72% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
Q2 2026
sent 07 Oct 2026
On the register
Units
100
Booked count
72
Escrow bank
ICICI BANK
Legal case
No
Form 5 · FY 2024–25
Rupees only where the ledger balanced on extract. Filed 31 Oct 2025.
Collected
₹7,63,72,707
Deposited
₹7,63,72,707 · 100.0% of collected
Withdrawn
₹7,14,00,000
Closing
₹50,72,707 · year-end, not today