ANANTA LIVING - DHARANI

On Track

BUILTECH HOUSING LLP · Apartments · MANKARA, Palakkad · K-RERA/PRJ/PKD/032/2024

Physical progress
68%
listing 68% · folder 60%
Proposed completion
29 Aug 2028
no date change on file
Units booked
15%
14 of 95
Quarterly update
Current
Q2 2026 · filed 07 Oct 2026 · -34d ago

As filed with K-RERA

Registration
K-RERA/PRJ/PKD/032/2024
granted 12 Feb 2024
Promoter
BUILTECH HOUSING LLP
Location
MANKARA, Palakkad, 678613
Type
Apartments
1 building(s)
Plot area
4,160 sqm
Registered floor area
7,341 sqm
≈ 79,013 sqft · residential 7,341 sqm · other 0 sqm
Units
95
95 residential
Project start
17 Dec 2023
Proposed completion
29 Aug 2028
Extension
—
Physical progress
68%
Financial progress
92%
Escrow bank
IDBI BANK
Financier
—
Complaint
No
Legal case
No
Authority order
No

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 07 Jul 2026
filed
Engineer Form 3
latest 07 Jul 2026
filed
CA Form 4
latest 07 Jul 2026
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

3 of 3 open on K-RERA
Filed 27 Oct 2025
file 181084
PDF on K-RERA · not parsed
Filed 27 Oct 2025
file 181085
PDF on K-RERA · not parsed
Filed 25 Oct 2024
file 137039
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

1 from register
TypeSignalSeveritySourceStatus
A
Spend running ahead of build
↳ Financial 92% vs physical 68%
MediumK-RERAOpen