Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
GLOBAL MISTY HILLS
On TrackStatus is from the dates they filed. Not a court finding.
Building
GLOBAL MISTY HILLS
Who is building it
GLOBAL HABITAT PRIVATE LIMITED
Official number
K-RERA/PRJ/KKD/128/2023 · 27 Jul 2023
Where
KURUVATTOOR, Kozhikode, 673017
Type
Villas
Promised ready date
30 Apr 2027
they did not change this date on file
How much they say is done
83%
this is what they filed on 11 Oct 2023
How many already sold
12 of 22
55% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
Q2 2026
sent 09 Jul 2026
On the register
Units
22
Booked count
12
Escrow bank
AXIS BANK
Legal case
No
Form 5 · FY 2023–24
Rupees only where the ledger balanced on extract. Filed 30 Oct 2024. Read via OCR.
Collected
₹60,44,679
Deposited
₹42,31,275 · 70.0% of collected
Withdrawn
₹41,90,000
Closing
₹41,275 · year-end, not today