ROYAL PINE
CompletedStatus is from the dates they filed. Not a court finding.
Building
ROYAL PINE
Who is building it
MALABAR DEVELOPERS PVT LTD
Official number
K-RERA/PRJ/KKD/120/2023 · 07 Jul 2023
Where
KASABA, Kozhikode, 673006
Type
Apartments
Promised ready date
13 Jan 2021
they did not change this date on file
How much they say is done
100%
they have not filed how much is done
How many already sold
0 of 61
0% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
61
Booked count
0
Escrow bank
NA
Legal case
No
Certificate note