Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
MELUHA MELODY
OverdueStatus is from the dates they filed. Not a court finding.
Building
MELUHA MELODY
Who is building it
MELUHA HOMES
Official number
K-RERA/PRJ/ERN/074/2023 · 26 Apr 2023
Where
KAKKANAD, Ernakulam, 682030
Type
Apartments
Promised ready date
30 Sept 2025
11 months past this date · they did not change it on file
How much they say is done
90%
this is what they filed on 12 Oct 2023
How many already sold
9 of 32
28% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
Q1 2025
sent 04 Jul 2025
On the register
Units
32
Booked count
9
Escrow bank
HDFC BANK LTD
Legal case
No