THE LAURELS BY FAVOURITE HOMES

Completed

FAVOURITE CONSTRUCTIONS PRIVATE LIMITED · Apartments · KADAKAMPALLY, Thiruvananthapuram · K-RERA/PRJ/TVM/004/2023

Physical progress
100%
not filed
Proposed completion
30 Jun 2026
no date change on file
Units booked
81%
80 of 99
Quarterly update
N/A
Q4 2025 · filed 07 Apr 2026 · 149d ago

As filed with K-RERA

Registration
K-RERA/PRJ/TVM/004/2023
granted 07 Jan 2023
Promoter
FAVOURITE CONSTRUCTIONS PRIVATE LIMITED
Location
KADAKAMPALLY, Thiruvananthapuram, 695029
Type
Apartments
1 building(s)
Plot area
3,642 sqm
Registered floor area
18,914 sqm
≈ 2,03,593 sqft · residential 18,914 sqm · other 0 sqm
Units
99
99 residential
Project start
23 Dec 2022
Proposed completion
30 Jun 2026
Extension
—
Physical progress
100%
Project completed and occupancy certificate obtained.
Financial progress
96%
Project resulted in savings of 4% from original estimation
Escrow bank
STATE BANK OF INDIA
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

5 of 5 filed
Architect Form 2
latest 07 Apr 2026
filed
Engineer Form 3
latest 07 Apr 2026
filed
CA Form 4
latest 07 Apr 2026
filed
Promoter Form 6
latest 26 Jun 2026
filed
Occupancy certificate
on file
filed

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

3 of 3 open on K-RERA
Collected FY 2024–25
₹29.8 Cr
₹29,80,49,642 as filed
Deposited
₹21.9 Cr
73.6% of collected
Withdrawn
₹21.9 Cr
from the separate account
Closing (year-end)
₹1.5 L
FY 2024–25 closing — not today’s balance
Separate account

FY 2024–25 Form 5 · as filed 31 Oct 2025 · PDF on K-RERA

Read Form 5 on K-RERA →
Opening
₹179
Collected from allottees
₹29,80,49,642
Deposited in separate account
73.6% of collected
₹21,94,77,898
Withdrawn
₹21,93,23,717
Closing
₹1,54,360
withdrawn ₹21,93,23,717year-end leftover ₹1,54,360

Closing is 0.1% of money that went through the separate account (opening + deposited). 73.6% of collected from allottees was deposited into that account as filed. Year-end figure on the CA certificate — not a live balance. Drawn at true scale. Source: Form 5 on K-RERA.

FY 2024–25
filed 31 Oct 2025 · file 181635
₹29,80,49,642 in
FY 2023–24
filed 05 Nov 2024 · file 138307
₹20,13,09,675 in
FY 2022–23
filed 31 Oct 2023 · file 101102
₹6,85,44,698 in

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

0 from register
No rows from the register.