As-filed extract · not an official certificate

Snapshot 12 Oct 2026

Check rera.kerala.gov.in

THANA SQUARE

Completed

Status is from the dates they filed. Not a court finding.

Building
THANA SQUARE
Who is building it
THANA SQUARE
Official number
K-RERA/PRJ/KNR/212/2022 · 20 Dec 2022
Where
PALLIKKUNNU, Kannur, 670012
Type
Commercial
Promised ready date
31 May 2014
they did not change this date on file
How much they say is done
100%
they have not filed how much is done
How many already sold
68 of 106
64% flats sold
Complaints
10
8 already decided
Last update to K-RERA
not needed
project is closed on the register

On the register

Units
106
Booked count
68
Escrow bank
NA
Legal case
Yes

Complaints before K-RERA · 10

152/2025 · Authority
pending
22/2024 · Authority
pending
267/2022 · Authority
final order
266/2022 · Authority
final order
262/2022 · Authority
final order
261/2022 · Authority
final order
260/2022 · Authority
final order
259/2022 · Authority
final order

+2 more on the site

Copied from public Kerala RERA filings. Independent. Not K-RERA. Not legal advice. Status is derived from filed dates and percents. Dash means missing on this snapshot. Documents stay on the portal — we link, we do not host.

Check rera.kerala.gov.in · this project folder · live page.