Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
GRAND MAPLE
CompletedStatus is from the dates they filed. Not a court finding.
Building
GRAND MAPLE
Who is building it
MALABAR DEVELOPERS PVT LTD
Official number
K-RERA/PRJ/KTM/146/2022 · 31 Aug 2022
Where
KAIPPUZHA, Kottayam, 686001
Type
Apartments
Promised ready date
27 Feb 2019
they did not change this date on file
How much they say is done
100%
they have not filed how much is done
How many already sold
0 of 73
0% flats sold
Complaints
2
2 already decided
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
73
Booked count
0
Escrow bank
NA
Legal case
Yes
Certificate note
The registration is valid only for the Residential project mentioned in the Building permit issued by Kottayam Municipality No. PW4/PW7/BA/334/13-14 dated 17/2/14
Complaints before K-RERA · 2
62/2022 · Authority
final order
202/2021 · Adjudicating Officer
final order