ZURA LUXURY LIVING
OverdueKad Builders And Developpers Pvt LtdEW · Apartments · MUTTATHODI, Kasaragod · K-RERA/PRJ/KSD/120/2022
Physical progress
30%
filed 16 Aug 2023
Proposed completion
30 Jul 2026
1 months past
Units booked
18%
16 of 90
Quarterly update
Current
Q1 2026 · filed 12 Jul 2026 · 53d ago
As filed with K-RERA
Registration
K-RERA/PRJ/KSD/120/2022
granted 18 Jul 2022
Promoter
Kad Builders And Developpers Pvt LtdEW
Location
MUTTATHODI, Kasaragod, 671123
Type
Apartments
2 building(s)
Plot area
5,504 sqm
Registered floor area
13,334 sqm
≈ 1,43,526 sqft · residential 13,334 sqm · other 0 sqm
Units
90
90 residential
Project start
03 Mar 2021
Proposed completion
30 Jul 2026
Extension
—
Physical progress
30%
work done 25% of the total project
Financial progress
26%
No any amount collected
Escrow bank
Canara Bank
Financier
—
Complaint
—
Legal case
No
Authority order
—
Folder noticeboard
3 of 5 filed
Architect Form 2
latest 22 Jun 2023
Engineer Form 3
latest 22 Jun 2023
CA Form 4
latest 22 Jun 2023
Promoter Form 6
unable to find
Occupancy certificate
unable to find
Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.
Certificate note
No conditions recorded on the certificate.
Same district, same year
Form 5 · statement of accounts
4 of 4 open on K-RERA
Filed 04 Nov 2024
file 138161
Filed 02 Nov 2024
file 138102
Filed 01 Nov 2024
file 138038
Filed 30 Oct 2024
file 137605
Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.
Complaints before K-RERA
No complaints on the public list.
RAID
1 from register
| Type | Signal | Severity | Source | Status |
|---|---|---|---|---|
| R | 1 months past proposed completion ↳ Proposed 2026-07-30, physical progress 30% | Medium | K-RERA | Open |