Completed

Thrissur Builders Private Limited · Apartments · THRISSUR, Thrissur · K-RERA/PRJ/211/2021

Physical progress
100%
filed 28 Oct 2022
Proposed completion
31 Dec 2020
no date change on file
Units booked
100%
64 of 61
Quarterly update
N/A
never filed

As filed with K-RERA

Registration
K-RERA/PRJ/211/2021
granted 18 Jul 2022
Promoter
Thrissur Builders Private Limited
Location
THRISSUR, Thrissur, 680004
Type
Apartments
1 building(s)
Plot area
2,355 sqm
Registered floor area
9,389 sqm
≈ 1,01,064 sqft · residential 9,389 sqm · other 0 sqm
Units
61
61 residential
Project start
—
Proposed completion
31 Dec 2020
Extension
—
Physical progress
100%
Financial progress
100%
WORK COMPLETED AND HANDED OVER THE PROJECT
Escrow bank
NOT APPLICABLE
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

2 of 5 filed
Architect Form 2
unable to find
not found
Engineer Form 3
unable to find
not found
CA Form 4
unable to find
not found
Promoter Form 6
latest 29 Apr 2022
filed
Occupancy certificate
on file
filed

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

No Form 5 on the public noticeboard for this project. That is also a fact.

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

0 from register
No rows from the register.