Enthayi?
As-filed extract · not an official certificate
Snapshot 12 Oct 2026
Check rera.kerala.gov.in
Sophia Elanza
CompletedStatus is from the dates they filed. Not a court finding.
Building
Sophia Elanza
Who is building it
—
Official number
K-RERA/PRJ/ERN/093/2022 · 28 May 2022
Where
VENGOLA, Ernakulam, 683556
Type
Villas
Promised ready date
20 May 2023
they did not change this date on file
How much they say is done
100%
this is what they filed on 13 Jan 2023
How many already sold
0 of 8
0% flats sold
Complaints
none on file
no complaint on the public list
Last update to K-RERA
not needed
project is closed on the register
On the register
Units
8
Booked count
0
Escrow bank
HDFC BANK LIMITED
Legal case
No
Certificate note
The promoter shall upload in the web portal, the registered Joint venture agreement within three months from the date of issue of registration certificate
Form 5 · FY 2021–22
Rupees only where the ledger balanced on extract. Filed 28 Nov 2022. Read via OCR.
Collected
₹3,23,85,000
Deposited
₹0 · 0.0% of collected
Withdrawn
₹0
Closing
₹0 · year-end, not today