SANROYAL ADONIA
OverdueStatus is from the dates they filed. Not a court finding.
Building
SANROYAL ADONIA
Who is building it
SANROYAL BUILDERS AND CONTRACTORS PVT LTD
Official number
K-RERA/PRJ/032/2020 · 04 Mar 2022
Where
MENAMKULAM, Thiruvananthapuram, 695582
Type
Apartments
Promised ready date
24 Jul 2025
14 months past this date · they did not change it on file
How much they say is done
97%
this is what they filed on 19 Dec 2022
How many already sold
57 of 81
70% flats sold
Complaints
2
2 already decided
Last update to K-RERA
Q2 2026
sent 25 Sept 2026
On the register
Units
81
Booked count
57
Escrow bank
ICICI
Legal case
No
Complaints before K-RERA · 2
68/2024 · Authority
final order
236/2022 · Authority
final order