Indraneelam Vantage

On Track

Indraneelam Builders · Villas · GURUVAYUR, Thrissur · K-RERA/PRJ/171/2021

Physical progress
89%
filed 10 Oct 2023
Proposed completion
30 Apr 2027
no date change on file
Units booked
100%
11 of 2
Quarterly update
Current
Q2 2026 · filed 06 Oct 2026 · -33d ago

As filed with K-RERA

Registration
K-RERA/PRJ/171/2021
granted 22 Nov 2021
Promoter
Indraneelam Builders
Location
GURUVAYUR, Thrissur, 680101
Type
Villas
13 building(s)
Plot area
2,223 sqm
Registered floor area
1,503 sqm
≈ 16,175 sqft · residential 1,503 sqm · other 0 sqm
Units
2
2 residential
Project start
—
Proposed completion
30 Apr 2027
Extension
—
Physical progress
89%
Financial progress
85%
Escrow bank
South Indian Bank
Financier
NA
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

3 of 5 filed
Architect Form 2
latest 05 Jul 2025
filed
Engineer Form 3
latest 05 Jul 2025
filed
CA Form 4
latest 05 Jul 2025
filed
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

6 of 6 open on K-RERA
Filed 05 Jul 2025
file 163384
PDF on K-RERA · not parsed
Filed 29 Oct 2024
file 137519
PDF on K-RERA · not parsed
Filed 30 Oct 2023
file 100892
PDF on K-RERA · not parsed
Filed 27 Apr 2023
file 87864
PDF on K-RERA · not parsed
Filed 26 Oct 2022
file 74727
PDF on K-RERA · not parsed
Filed 21 Mar 2022
file 50662
PDF on K-RERA · not parsed

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

0 from register
No rows from the register.