CAMELOT

Overdue

APSTONE INFRASTRUCTURE Pvt Ltd · Villas · CHENGANNUR, Alappuzha · K-RERA/PRJ/135/2021

Physical progress
0%
filed 12 Jan 2023
Proposed completion
31 Dec 2024
20 months past
Units booked
0%
0 of 15
Quarterly update
Never
never filed

As filed with K-RERA

Registration
K-RERA/PRJ/135/2021
granted 16 Aug 2021
Promoter
APSTONE INFRASTRUCTURE Pvt Ltd
Location
CHENGANNUR, Alappuzha, 689121
Type
Villas
15 building(s)
Plot area
4,485 sqm
Registered floor area
3,011 sqm
≈ 32,409 sqft · residential 2,732 sqm · other 279 sqm
Units
15
14 residential · 1 commercial
Project start
01 Jul 2020
Proposed completion
31 Dec 2024
Extension
—
Physical progress
0%
Financial progress
10%
No sale has yet materialised for the project due to covid delays
Escrow bank
AXIS BANK
Financier
—
Complaint
—
Legal case
No
Authority order
—

Folder noticeboard

0 of 5 filed
Architect Form 2
unable to find
not found
Engineer Form 3
unable to find
not found
CA Form 4
unable to find
not found
Promoter Form 6
unable to find
not found
Occupancy certificate
unable to find
not found

Peeked from the public folder. “Unable to find” means we did not see that slot in this pull — not a finding that the promoter withheld it. PDFs stay on K-RERA.

Certificate note

No conditions recorded on the certificate.

Form 5 · statement of accounts

No Form 5 on the public noticeboard for this project. That is also a fact.

Annual CA report on the separate account for a stated financial year. Rupees only when the ledger balances on extract. Closing is year-end, not today. We link the filing on K-RERA; we do not host the PDF. Form 5 coverage.

Complaints before K-RERA

No complaints on the public list.

RAID

2 from register
TypeSignalSeveritySourceStatus
R
20 months past proposed completion
↳ Proposed 2024-12-31, physical progress 0%
HighK-RERAOpen
D
No quarterly update ever filed
MediumK-RERAOpen